CONTROL BUILDING

CENEX-HARVEST STATES REFINERY

CHS hired Space Planning for People to design, outside the perimeter of the plant itself, a new Central Control Building.  As this facility represents the "heart" of the refining operations, the Control Center has been designed to remain operational throughout any emergency.  Thus, the enclosure is of blast-resistant design, and back-up power generators are provided.

 

Despite the high degree of specialized research required for this unique facility, the building was programmed, designed, bid, and constructed within fourteen months.

    

LOCATION

     Laurel, Montana

 

CLIENT

     CHS Refinery

     Mr. Pat Kimmet

 

SIZE

     7,120 s.f. – Main Floor

     6,640 s.f. – Second Floor

 

CONSTRUCTION COST

     $3,620,000